Project status: This morning we lifted the eastern beams 1 and 2 and inserted rollers. It was hard work because it is the end with little space and so the lifting work must be done lying down ..... no help from the leg muscles!
Tomorrow we can lift the north side of the building and commence pulling it over. This will be much easier as it doesn't require going underneath the building.